Option 2 - Upgrade

  1. After starting the fail over and rebuild process to rebuild the current secondary Controller, the following message displays if the Controller HA failover job was successful:

    Note: If using HATK, you can check the current state of the primary and secondary Controllers by running this script on each server: <controller_home>/HA/appdstatus.sh
    1. Select Continue to begin incremental replication for the rebuild and continue to Step 2.
    2. Otherwise, if you need to cancel the Failover & Rebuild Secondary process, select Abort to exit. The following confirmation message displays:

    3. Select OK to confirm cancellation.
  2. If the Controller incremental replication job was successful, the following message displays:

    Select Continue to finalize the replication to the secondary Controller.

  3. If the Controller finalize replication job completed successfully, the following message displays:

    Select Done.

This completes rebuilding the current secondary server so both Controllers in the HA pair are now replicating data.